Wednesday, 20 July 2016 07:55

September start for Ruataniwha?

Written by  Pam Tipa
Work could start as soon as September on the Ruataniwha water storage scheme. Work could start as soon as September on the Ruataniwha water storage scheme.

Work could start as soon as September on the Ruataniwha water storage scheme if consents and land requirements fall into the place.

This is the message from Andrew Newman, chief executive of the Hawke's Bay Regional Investment Company.

"If everything went unconditional and we had the small amount of DoC land we need, things would start immediately after financial close – probably September," he told Rural News.

"That remains speculative. We have to finish the financing condition and resolve residual issues."

In the development phase the company needs to meet four conditions for the council to approve $80 million development funding, Newman says. These are consents, sufficient water contracted, a construction contractual form which allocates risk correctly and the financing. The first three have been met and the company is now confirming financing conditions with the council.

"We are right in the middle of closing out now; we are probably about six to eight weeks away from doing that," he says.

A big push on signing up farmers and growers in March and April resulted in numbers in "pretty reasonable shape". They expect to contract more water and will give it another push before the end of August.

The cost of the dam, distribution network, pipes, pumps and the canals and development is about $340m. It will take about three and a half years to complete.

The scheme will be a 93m cu.m reservoir on the upper Makaroro River, storing water during winter. Water will be released from the reservoir to improve river flows in the Tukituki catchment in summer for river life and for irrigation.

The council condition was that 40m cu.m had to be signed up by farmers and growers; at the time of speaking to Rural News they had 42.6m cu.m. Contractual negotiations in process will take them to 48-49m cu.m. Signatures now total 190, a number expected to grow a lot in the next few weeks.

There are 30-odd land transactions involved. A couple of private land deals are yet to be concluded and that is happening now, Newman says.

Beyond that they have a land exchange with DoC, which has agreed to it, but Forest and Bird has run a judicial review process. It first went to the High Court which found in favour of the land exchange. Forest and Bird has now taken that to the Court of Appeal; the decision is pending.

In addition to the $340m in dam and distribution infrastructure costs, the amount of onfarm development capital required will depend on use of the scheme. If there was 4000ha or more of intense, permanent horticulture like trees and vines, a total of $550m could be needed extra to off-farm capital. But that would be funded by irrigators and landowners.

If the land were not so horticulture-intensive, those onfarm costs may total about $350m but it depends what land use emerges.

More like this

Ruataniwha dam busted?

The future of the controversial Ruataniwha water storage dam in central Hawkes Bay is in limbo, following the recent local body election.

A damn load of emotional effluent

The Ruataniwha water storage scheme saga has gone far beyond soap opera territory: fantasy has long since replaced fact, the noisy quashing any sense.

Ruataniwha setback?

A controversial land swap deal which would have advanced the Ruataniwha dam scheme may now not go ahead.

Dam good decision — Editorial

This month's decision by the Hawke's Bay Regional Council (HBRC) confirming its intention to invest in the Ruataniwha water storage scheme is a good one.

Featured

Feds make case for rural bank lending probe

Bankers have been making record profits in the last few years, but those aren’t the only records they’ve been breaking, says Federated Farmers vice president Richard McIntyre.

National

Fonterra unveils divestment plan

Fonterra is exploring full or partial divestment options for its global Consumer business, as well as its integrated businesses Fonterra…

Fonterra appoints new CFO

Fonterra has appointed a new chief financial officer, seven months after its last CFO’s shock resignation.

Machinery & Products

GPS in control

In a move that will make harvesting operations easier, particularly in odd-shaped paddocks, Kuhn has announced that GPS section control…

» Latest Print Issues Online

The Hound

Wrong, again!

OPINION: This old mutt well remembers the wailing, whining and gnashing of teeth by former West Coast MP and Labour…

Reality check

OPINION: Your canine crusader gets a little fed up with the some in media, union hacks, opposition politicians and hard-core…

» Connect with Rural News

» eNewsletter

Subscribe to our weekly newsletter